Site Map | | Loaf N’ Jug Advantex Wastewater System Installation Bailey, Colorado | During the summer of 2002, an AdvanTex™ Treatment System was installed by SRC at the Crow Hill Loaf N’ Jug in Bailey, Colorado. The system was designed to treat an average daily wastewater flow of 1200 GPD from the gasoline and convenience store.
The system includes a 1000 gallon grease interceptor, 4000 gallons of septic tank capacity, a 1500 gallon recirculation tank, and four AX20 textile filter assemblies. The treated effluent is dosed to a pressure distributed drain field.
The treatment system was installed for nitrogen reduction and to pre-treat the moderate strength septic tank effluent prior to discharge to the underlying fractured granite bedrock.
Permitting Authority: Park County Health Department Project Engineer: CHURCH & Associates, Inc. Installer: SRC Excavating Operator: SCG Enterprises, Inc. |  | |  |
|